From infrastructure setup to a platform ready for commercialisation and replication — how the work is phased across the project’s full duration.
36 MONTHS · OCT 2025 – SEP 2028
Three years, seven work streams.
WORK PLAN AT A GLANCE
Seven streams, mapped across 36 months.
YEAR BY YEAR
Milestones along the way.
- Establish project governance and infrastructure
- Integrate and preprocess datasets
- Develop and test initial AI models
Milestone — Central Data Warehouse operational; baseline models validated.
- Complete AI model training and optimisation
- Build prototype software platform
- Begin pilot testing with HEP ODS
Milestone — First functional prototype and field validation achieved.
- Final validation, impact analysis and scaling roadmap
- Technology transfer to ADNET and deployment at HEP ODS
- Dissemination of results and scientific publication
Milestone — System ready for commercialisation and replication (TRL 7–8).
See what each milestone actually produces.
Public reports, datasets and dissemination material, published as the project progresses.