From infrastructure setup to a platform ready for commercialisation and replication — how the work is phased across the project’s full duration.

Year 1 Year 2 Year 3
Infrastructure Equipping
M1–M6
Research Activities
M1–M36
Knowledge & Tech Transfer
M1–M36
Capacity Building & Dissemination
M12–M36
Market Analysis & Validation
M1–M12
Promotion & Visibility
M1–M36
Project Management
M1–M36
Delivery-focused streams Continuous / cross-cutting streams
  • Establish project governance and infrastructure
  • Integrate and preprocess datasets
  • Develop and test initial AI models

Milestone — Central Data Warehouse operational; baseline models validated.

  • Complete AI model training and optimisation
  • Build prototype software platform
  • Begin pilot testing with HEP ODS

Milestone — First functional prototype and field validation achieved.

  • Final validation, impact analysis and scaling roadmap
  • Technology transfer to ADNET and deployment at HEP ODS
  • Dissemination of results and scientific publication

Milestone — System ready for commercialisation and replication (TRL 7–8).